Kitchen worktop producer Kemie had three different sites in Asten. These were merged into one stunning site with a 8,200 m2 hall and around 1,400 m2 of office space at the former Vion site on Graandijk in Helmond. 

We produced and assembled the steel structure from approximately 549,000 kg of steel for this Heembouw Breda BV contract. We also installed the hollow-core slab floor, concrete panels and aerated concrete walls.